Commvault® software offers a great deal of flexibility for controlling job activity. Data protection, recovery, and administrative jobs can be temporarily disabled and then re-enabled at a specific data and time. Activity control can be set for the entire CommCell® environment, client computer group, and client levels.


Job activity key points:

  • If activity is disabled in a parent object of the CommCell tree, activity is automatically disabled for any child objects.
  • Activity can be disabled until manually enabled or set to automatically re-enable at a specific date and time.
  • If activity is enabled for a parent object in the CommCell tree, activity can be enabled or disabled for any child objects.
  • When activity is disabled or enabled, the icon where the activity was set changes to reflect the current activity state.

Which Activity can be Controlled?

  • All activity for the entire CommCell® environment can be enabled / disabled.
  • Disabling activity at the CommCell level will disable all activity in the CommCell environment.
  • Enabling (default) allows activity to be controlled at child levels.


Activity control at the various levels of the CommCell® environment

Activity that can be enabled or disabled

CommCell

Client Group

Client

Agent

Backup Set

Subclient

All activity
 

Yes

No

No

No

No

No

Data Management

Yes

Yes

Yes

Yes

 

Yes

Data Recovery
 

Yes

Yes

Yes

Yes

No

Yes

Auxiliary Copy
 

Yes

No

No

No

No

No

Data Aging

Yes

 

Yes

No

No

No

Schedule Activity

Yes

No

Yes (enabled / disabled through schedule view for client)

Yes (enabled / disabled through schedule view for an agent)

Yes (enabled / disabled through schedule view for backup set)

Yes (enabled / disabled through schedule view for subclient)


Enabling or Disabling CommCell Activity

Disabling Job Activity

If job activity is disabled at any level within the CommCell® tree, it will automatically disable activity for any child objects within the tree. Activity cannot be overridden at any child levels.


Example: A client computer group representing clients for a specific location is disabled for maintenance. By disabling activity at the group level, all clients within the group are automatically disabled.

Job Activity Control - Demo

View file
nameJobMgmt-vidCC-ActivityControl.mp4
pageJob and Resource Management - CommCell® Console
height150



To control activity globally

1 - In the CommCell® browser, right-click the CommServe® server and select Properties.

2 - Uncheck to disable all activity.

3 - Uncheck any box to disable specific activity type.


Enabling Job Activity

If job activity is enabled at any level within the CommCell® tree activity can be disabled at any child level object within the tree.


Example: A specific client has a maintenance window scheduled. By disabling the activity for that client, no operations will run. All other clients within the group will operate normally.




To control activity for a client

1 - In the CommCell® browser, right-click the client and select Properties.

2 - Uncheck to disable activity.


Enabling After Delay

If activity is disabled at any level in the CommCell® tree the option 'Enable after a Delay' can be used to set a date and time where activity is automatically re-enabled.




To automatically re-enable activity for a client

1 - In the CommCell® browser, right-click the client and select Properties.

2 - Uncheck to disable activity.

3 - Click to re-enable activity automatically.

4 - Check and set the time at which activity is re-enabled.